June 21, 2017 – Formal Consultation meeting held at the City of Hamilton

October 11, 2017 – Application for Zoning By-Law Amendment submitted to the City of Hamilton

November 6, 2017 – Application for Zoning By-Law Amendment deemed complete by the City of Hamilton

November 17, 2017 – Notice of circulation to the surrounding public

December 14, 2017 – Site Plan Control application submitted to the City of Hamilton. UrbanSolutions and the project team are working with City staff in securing final site plan approval.

June 13, 2018 – Application for permanent closure of the alleyway approved by City of Hamilton Council.

September 4, 2018 – Public Meeting at Planning Committee.

September 26, 2018 – Official Plan Amendment and Zoning By-law Amendment passed by City Council.

October 23, 2018 – Site Plan Control application submitted to the City of Hamilton. UrbanSolutions and the project team are working with City staff in securing final site plan approval.